AWS Certified Solutions Architect - Associate SAA-C03 — Question 300
Topic 1 · Question 300 of 1019
Topic 1 · Question 300
A company needs to migrate a legacy application from an on-premises data center to the AWS Cloud because of hardware capacity constraints. The application runs 24 hours a day, 7 days a week. The application’s database storage continues to grow over time. What should a solutions architect do to meet these requirements MOST cost-effectively?