AWS Certified Solutions Architect - Professional SAP-C02 — Question 339
Topic 1 · Question 339 of 529
Topic 1 · Question 339 · Select all that apply
A company is migrating a legacy application from an on-premises data center to AWS. The application consists of a single application server and a Microsoft SQL Server database server. Each server is deployed on a VMware VM that consumes 500 TB of data across multiple attached volumes. The company has established a 10 Gbps AWS Direct Connect connection from the closest AWS Region to its on-premises data center. The Direct Connect connection is not currently in use by other services. Which combination of steps should a solutions architect take to migrate the application with the LEAST amount of downtime? (Choose two.)
Select 2 answers to reveal the result.