AWS Certified SysOps Administrator - Associate SOA-C02 — Question 271

Topic 1 · Question 271 of 477

Topic 1 · Question 271 · Select all that apply

A SysOps administrator needs to design a disaster recovery (DR) plan for an application on AWS. The application runs on Amazon EC2 instances behind an Application Load Balancer (ALB). The instances are in an Auto Scaling group. The application uses an Amazon Aurora PostgreSQL database. The recovery time objective (RTO) and recovery point objective (RPO) are 15 minutes each. Which combination of steps should the SysOps administrator take to meet these requirements MOST cost-effectively? (Choose two.)

Select 2 answers to reveal the result.