CompTIA Project+ (PK0-005) PK0-005 — Question 101
Topic 1 · Question 101 of 187
Topic 1 · Question 101
During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?