CompTIA Project+ (PK0-005) PK0-005 — Question 107
Topic 1 · Question 107 of 187
Topic 1 · Question 107
As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT?