CompTIA Project+ (PK0-005) PK0-005 — Question 135
Topic 1 · Question 135 of 187
Topic 1 · Question 135
The project kickoff concluded, and the sponsor indicated that the recently hired summer interns are authorized to work on the project. Which of the following should the project manager do NEXT?