CompTIA Project+ (PK0-005) PK0-005 — Question 152

Topic 1 · Question 152 of 187

Topic 1 · Question 152

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do NEXT to comply with the new legislation?