CompTIA Project+ (PK0-005) PK0-005 — Question 16

Topic 1 · Question 16 of 187

Topic 1 · Question 16

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?