CompTIA Project+ (PK0-005) PK0-005 — Question 175
Topic 1 · Question 175 of 187
Topic 1 · Question 175
A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?