CompTIA Project+ (PK0-005) PK0-005 — Question 18
Topic 1 · Question 18 of 187
Topic 1 · Question 18
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?