CompTIA Project+ (PK0-005) PK0-005 — Question 18

Topic 1 · Question 18 of 187

Topic 1 · Question 18

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?