CompTIA Project+ (PK0-005) PK0-005 — Question 180
Topic 1 · Question 180 of 187
Topic 1 · Question 180
During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?