A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains: Purpose - Scope of work - Location of work - Period of performance - Deliverables schedule - Applicable standards - Acceptance criteria - Special requirements - Payment schedule - Which of the following documents did the client provide to the project manager?