CompTIA Project+ (PK0-005) PK0-005 — Question 88
Topic 1 · Question 88 of 187
Topic 1 · Question 88
A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take?