CompTIA Project+ (PK0-005) PK0-005 — Question 96
Topic 1 · Question 96 of 187
Topic 1 · Question 96
In the kickoff meeting, a project manager announced the project will use a tool to store documents, artifacts, and any other data relevant to the project. The tool will perform version control, maintain retention data, and archive destruction or historical information. Which of the following is being described?