You are configuring project metrics for dashboards in Azure DevOps. You need to configure a chart widget that measures the elapsed time to complete work items once they become active. Which of the following is the widget you should use?
- ACumulative Flow Diagram
- BBurnup
- CCycle time (correct answer)
- DBurndown
Reveal answer & explanationHide answer
The correct answer is C. Option C: Cycle time.