CompTIA Project+ (PK0-005) PK0-005 — Question 73
Topic 1 · Question 73 of 187
Topic 1 · Question 73
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Topic 1 · Question 73 of 187
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?