CompTIA Project+ (PK0-005) PK0-005 — Question 74

Topic 1 · Question 74 of 187

Topic 1 · Question 74

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

View community discussion →