Topic 1 Β· Question 182

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project’s timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

  • ASmoothing
  • BConfronting
  • CForcing
  • DCompromising (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Compromising

Topic 1 Β· Question 183

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

  • AProject status report
  • BProject evaluation review
  • CProject management software (correct answer)
  • DRequirements traceability matrix
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Project management software

Topic 1 Β· Question 184

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

  • ADiscovery
  • BExecution
  • CInitiating (correct answer)
  • DPlanning
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Initiating

Topic 1 Β· Question 185

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete next?

  • ADocument the request in the change control log.
  • BPerform a Monte Carlo simulation.
  • CConduct an impact assessment.
  • DImplement the change. (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Implement the change.

Topic 1 Β· Question 186

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

  • AStatus report
  • BIssue log
  • CRisk report (correct answer)
  • DRisk register
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Risk report

Topic 1 Β· Question 187

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

  • AExploit
  • BShare (correct answer)
  • CTransfer
  • DAccept
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Share

Topic 1 Β· Question 188

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

  • AIntegrity
  • BSecurity
  • CArchival (correct answer)
  • DLessons learned
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Archival