A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do NEXT?
- ABuy a replacement for the faulty equipment.
- BGet the maintenance team to resolve the issue.
- CEscalate the issue to the project sponsor.
- DRate the severity of the impact the issue has on the project. (correct answer)
Reveal answer & explanationHide answer
The correct answer is D. Option D: Rate the severity of the impact the issue has on the project.