Topic 1 Β· Question 162

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do NEXT?

  • ABuy a replacement for the faulty equipment.
  • BGet the maintenance team to resolve the issue.
  • CEscalate the issue to the project sponsor.
  • DRate the severity of the impact the issue has on the project. (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Rate the severity of the impact the issue has on the project.

Topic 1 Β· Question 163

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform FIRST?

  • ADefine the WBS.
  • BDevelop a RAM. (correct answer)
  • CManage the vendors.
  • DAssess the resource pool.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Develop a RAM.

Topic 1 Β· Question 164

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do FIRST?

  • AEscalate the change to the CCB.
  • BReview the requested change. (correct answer)
  • CDocument the change recommendations.
  • DValidate the implementation of the requested change.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Review the requested change.

Topic 1 Β· Question 165 Β· Select all that apply

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Choose two.)

  • ACreating a backlog
  • BManaging the quality of deliverables
  • CUpdating the issue log
  • DPerforming a risk assessment
  • EValidating the deliverables (correct answer)
  • FReconciling the project budget (correct answer)
Reveal answer & explanation
Correct answer: E, F

The correct answer is E, F. Option E: Validating the deliverables Option F: Reconciling the project budget

Topic 1 Β· Question 166

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

  • AInitiation
  • BClosing
  • CExecution
  • DPlanning (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Planning

Topic 1 Β· Question 167

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer: β€’ Two developers β€’ High uncertainty about existing systems β€’ Risk of frequent requirement changes β€’ Tight deadlines Which of the following project methodologies would be BEST to use in this situation?

  • APRINCE2
  • BScrum
  • CSAFe
  • DXP (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: XP

Topic 1 Β· Question 168

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite FIRST?

  • ARFI (correct answer)
  • BRFP
  • CRFQ
  • DRFB
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: RFI

Topic 1 Β· Question 169

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the BEST document for the company to use to obtain and compare information on cabling services and costs from various vendors?

  • ARFB
  • BRFQ
  • CRFI
  • DRFP (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: RFP

Topic 1 Β· Question 170

A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

  • AXaaS
  • BSaaS
  • CPaaS
  • DIaaS (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: IaaS

Explanation

Infrastructure as a service provides virtualized compute, storage, and networking while the customer manages the OS and applications.

Topic 1 Β· Question 171

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is BEST for determining this information?

  • APERT chart
  • BMilestone chart
  • CGantt chart (correct answer)
  • DBudget burndown chart
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Gantt chart

Topic 1 Β· Question 172

One of the key steps in controlling changes to software is obtaining approval. Which of the following statements BEST describes the reason for this key objective?

  • ATo send the appropriate customer notifications
  • BTo avoid a negative impact on other software functionalities (correct answer)
  • CTo ensure adequate resources are in place to implement the change
  • DTo confirm that the software is a business priority
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: To avoid a negative impact on other software functionalities

Topic 1 Β· Question 173

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

  • ARegression testing (correct answer)
  • BSmoke testing
  • CStress testing
  • DAutomation testing
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Regression testing

Topic 1 Β· Question 174

Which of the following can a project manager infer from the following velocity chart?

Exhibit 1 for question 174
  • AThe project is on schedule.
  • BThe project is ahead of schedule.
  • CThe project is behind schedule. (correct answer)
  • DThe project is at risk.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: The project is behind schedule.

Topic 1 Β· Question 175

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?

  • AGantt chart
  • BProject organization chart
  • CProgram Evaluation Review Technique chart
  • DMilestone chart (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Milestone chart

Topic 1 Β· Question 176

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date. Which of the following tools should the project manager use first to update the findings?

  • ADefect log
  • BChange log
  • CIssue log (correct answer)
  • DRisk log
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Issue log

Topic 1 Β· Question 177

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

  • AForcing
  • BAvoiding (correct answer)
  • CCompromising
  • DSmoothing
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Avoiding

Topic 1 Β· Question 178

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

  • AUse an on-premises project management scheduling tool.
  • BLimit access to members of the project team. (correct answer)
  • CMandate overtime to get the project completed sooner.
  • DEnsure all team members have signed a non-disclosure agreement.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Limit access to members of the project team.

Topic 1 Β· Question 179

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement. Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

  • ARisk register
  • BChange log
  • CTraceability matrix
  • DProject status report (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Project status report

Topic 1 Β· Question 180

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

  • ABaseline
  • BRBS
  • CWBS (correct answer)
  • DMilestones
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: WBS

Topic 1 Β· Question 181

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the following has the project manager identified?

  • ATechnological factors
  • BPoor sample data
  • CLanguage barriers
  • DScope creep (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Scope creep