To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which of following techniques is the project manager utilizing?
- AProcess modeling
- BBrainstorming
- CInterview (correct answer)
- DFocus group
Reveal answer & explanationHide answer
The correct answer is C. Option C: Interview