πŸ”

PK0-005 β€” questions

Page 7 of 10 Β· 187 total questions.

Topic 1 Β· Question 122

In an agenda for a kickoff meeting, some time is set aside to complete a document that identifies each member of the project, the members' roles and responsibilities for tasks, the milestones, and the key decisions. In which of the following should this data be documented?

  • ATOR
  • BWBS
  • CRAM (correct answer)
  • DSOW
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: RAM

Topic 1 Β· Question 123

During a project sprint, an analyst explains multiple situations the team encountered after the previous day's sessions. The analyst then lists the tasks that need to be completed before the end of the day. Which of the following meeting types is the team utilizing?

  • AStand-up meeting (correct answer)
  • BWorkshop meeting
  • CKick-off meeting
  • DPresentation meeting
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Stand-up meeting

Topic 1 Β· Question 124

A project manager reviews the watch list and notices the probability of occurrence has increased for one item listed in this document; consequently, frequent monitoring is required. Which of the following tools should the project manager update NEXT?

  • ADefect log
  • BStakeholder register
  • CIssue log
  • DRisk register (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Risk register

Topic 1 Β· Question 125

Which of the following IT elements allows developers to leverage existing code to integrate with other software systems?

  • ASaaS
  • BAPI (correct answer)
  • CDatabases
  • DEnd user applications
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: API

Topic 1 Β· Question 126

A stakeholder notices a typo in the project management plan, specifically the word manager was spelled β€œmanger”. Which of the following is the decision maker who can authorize the change so the correction can be made?

  • APM (correct answer)
  • BCCB
  • CSponsor
  • DBusiness analyst
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: PM

Topic 1 Β· Question 127

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM MOST likely perform?

  • ACall the previous PM for advice on risks and issues.
  • BAsk the project sponsor to provide previous final project report results.
  • CComplete the project charter using the other PM's subject matter expertise.
  • DUse existing artifacts and accommodate based on the current project success criteria. (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Use existing artifacts and accommodate based on the current project success criteria.

Topic 1 Β· Question 128

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take NEXT?

  • AAssign more resources to complete similar stories in the future.
  • BBreak the stories into workable items that can be completed within one sprint. (correct answer)
  • CExtend the sprint duration when required with the approval of the product owner.
  • DRelease the current progress into production and carry over the rest of the code for the next sprint.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Break the stories into workable items that can be completed within one sprint.

Topic 1 Β· Question 129

During the planning phase, a project manager held a meeting to discuss meeting days, meeting times, meeting frequency, and tools to use. Which of the following will the project manager use to document this data?

  • AProject communication plan (correct answer)
  • BProject charter
  • CProject management plan
  • DProject plan
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Project communication plan

Topic 1 Β· Question 130

During the course of a project, an unexpected event occurs that could ultimately benefit the company. Which of the following is the company employing if the company decides to take advantage of this opportunity?

  • AExploit (correct answer)
  • BEnhance
  • CAccept
  • DMitigate
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Exploit

Topic 1 Β· Question 131

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

  • AMitigate (correct answer)
  • BTransfer
  • CAccept
  • DShare
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Mitigate

Topic 1 Β· Question 132

Testing has been completed, and the new system is loaded in production and ready to be activated. Which of the following needs approval from the project sponsor?

  • AProject charter
  • BDeployment plan (correct answer)
  • CBusiness case
  • DRelease schedule
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Deployment plan

Topic 1 Β· Question 133

A project sponsor is notified that the committed turnaround time has been exceeded. The team member assigned to this item stated that the support of the management team was requested on time. Which of the following documents should be reviewed to understand the root cause of this situation?

  • ARACI
  • BSOW
  • CEscalation path (correct answer)
  • DCommunication plan
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Escalation path

Topic 1 Β· Question 134

During the kickoff meeting, a stakeholder raises a concern that an assigned responsibility is outside of the stakeholder's domain. Which of the following would MOST likely be the reason?

  • AThe communication plan is outdated.
  • BThe project manager did not assess the stakeholders.
  • CThe project manager did not update the risk register.
  • DThe statement of work does not reflect the impacted stakeholders. (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: The statement of work does not reflect the impacted stakeholders.

Topic 1 Β· Question 135

The project kickoff concluded, and the sponsor indicated that the recently hired summer interns are authorized to work on the project. Which of the following should the project manager do NEXT?

  • AHost a risk workshop with all stakeholders to complete an initial risk assessment.
  • BWork with the interns to develop a work breakdown structure and project schedule.
  • CConduct a skills assessment to determine the strengths and weaknesses of the staff. (correct answer)
  • DAssign the resources to project tasks and encourage them to begin work immediately.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Conduct a skills assessment to determine the strengths and weaknesses of the staff.

Topic 1 Β· Question 136

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to identify the level of engagement among project team members. Which of the following would be the BEST tool for the project manager to use?

  • AMeeting chat
  • BEmail
  • CReal-time survey (correct answer)
  • DWhiteboard
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Real-time survey

Topic 1 Β· Question 137

While defining technical requirements, the development team requested a tiered architecture setup. Which of the following types of environments BEST describes this architecture?

  • ASecurity environment
  • BNetwork environment (correct answer)
  • CRelease environment
  • DStage environment
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Network environment

Topic 1 Β· Question 138

A project manager reviews a new project charter and notices that the project objective is similar to a project that was done in the past. Which of the following actions should the project manager take?

  • AReview the existing artifacts and customize accordingly. (correct answer)
  • BUtilize the existing artifacts to manage the project.
  • CAsk the previous project manager for advice.
  • DNotify the sponsor that this project duplicates a prior project.
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Review the existing artifacts and customize accordingly.

Topic 1 Β· Question 139

Which of the following is a web template that is used to create websites?

  • AERP
  • BCRM
  • CEDRMS
  • DCMS (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: CMS

Topic 1 Β· Question 140

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

  • ASmoke test (correct answer)
  • BStress test
  • CPenetration test
  • DRegression test
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Smoke test

Topic 1 Β· Question 141

A project manager is performing planning tasks for a complex project at a small company. Which of the following items would be of GREATEST importance during planning?

  • ADefining the project objectives, scope, and success criteria (correct answer)
  • BAssessing the resources available for operational support after project implementation
  • CProviding updates and status reports to the project owner and stakeholders
  • DDeveloping a records management plan and reviewing existing project artifacts
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Defining the project objectives, scope, and success criteria

Showing questions 121–140 of 187 Β· Page 7 of 10