πŸ”

PK0-005 β€” questions

Page 6 of 10 Β· 187 total questions.

Topic 1 Β· Question 102

Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?

  • ANegotiate to get more of the team member's available time. (correct answer)
  • BAssign the team member to work overtime to finish the task.
  • CSpeed up completion of the task by assisting the team member.
  • DHave the project manager complete the task.
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Negotiate to get more of the team member's available time.

Topic 1 Β· Question 103

A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio. Which of the following should the manager use to accomplish this task?

  • ADashboard (correct answer)
  • BStatus report
  • CGantt chart
  • DEmail
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Dashboard

Topic 1 Β· Question 104

A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?

  • ATrust that the project requirements fully document the necessary compliances.
  • BMeet with the end users to learn more about the compliance requirements.
  • CResearch the compliance requirements related to the project to understand the implications. (correct answer)
  • DMake the QA specialist responsible for ensuring that the compliance requirements are met.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Research the compliance requirements related to the project to understand the implications.

Topic 1 Β· Question 105

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

  • ACompromising
  • BForcing
  • CSmoothing (correct answer)
  • DCollaborating
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Smoothing

Topic 1 Β· Question 106

A project manager is assigned to a large, complex project that is very new to the organization. Because of huge expenditures, the project cannot be cancelled after it starts. Which of the following is most important for the project manager to do FIRST?

  • ACarefully select the vendor.
  • BIdentify and evaluate risks. (correct answer)
  • CEstablish change management procedures.
  • DEvaluate the resource pool.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Identify and evaluate risks.

Topic 1 Β· Question 107

As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT?

  • AValidate the change implementation.
  • BImplement the change. (correct answer)
  • CConduct an impact assessment.
  • DCommunicate the change deployment.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Implement the change.

Topic 1 Β· Question 108

A project manager is discussing with team members sensitive project information that should not be disclosed outside of the office. Which of the following BEST describes this type of information?

  • AIntellectual property
  • BMarketing
  • CTrade secret (correct answer)
  • DTop secret
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Trade secret

Topic 1 Β· Question 109

Which of the following would be the MOST beneficial to determine whether a project has met the defined objectives?

  • ASchedule variance
  • BCost variance
  • CWork breakdown structure
  • DKey performance indicators (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Key performance indicators

Topic 1 Β· Question 110

A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?

  • AProposed solution design
  • BPreliminary scope statement (correct answer)
  • CResponsibility assignment matrix
  • DInitial budget baseline
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Preliminary scope statement

Topic 1 Β· Question 111

A project has been initiated to provide insurance forms for a company. A constraint for this project is that the insurance commission in each state where the company underwrites has to approve each form. Which of the following compliance considerations BEST describes this scenario?

  • ARegulatory impacts (correct answer)
  • BEnvironmental impacts
  • COrganizational impacts
  • DSensitive data types
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Regulatory impacts

Topic 1 Β· Question 112

During the execution of production for a bike, a PM was hired. One month later, the PM has been receiving multiple project report requests from stakeholders. Which of the following should the PM do FIRST?

  • ADiscuss the requests with the sponsor.
  • BPrepare and send the information.
  • CAssign this task to the project team.
  • DReview the communication plan. (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Review the communication plan.

Topic 1 Β· Question 113

A team member finds a malfunctioning procedure in the system that will take a considerable amount of time to fix. Which of the following should be done FIRST?

  • AUpdate the risk register
  • BDocument the finding in the change log.
  • CCreate a record in the issue log (correct answer)
  • DDetail a proposed solution.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Create a record in the issue log

Topic 1 Β· Question 114

A project team has identified a bug during user acceptance testing. Which of the following is the BEST method for communicating that bug to the development team?

  • ACall the development lead to discuss the fixes for the bug.
  • BInclude the bug issue as part of the status update for stakeholders.
  • CIssue a change request. (correct answer)
  • DAdd the bug issue to the project's risk register.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Issue a change request.

Topic 1 Β· Question 115

Internal project team members and a subject matter expert had a heated discussion about the client's needs. The deliverable is now at risk of being delayed. Which of the following should be notified LAST?

  • AProgram manager
  • BEnd user (correct answer)
  • CSteering committee
  • DProject sponsor
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: End user

Topic 1 Β· Question 116

Which of the following methodologies/frameworks should be used when incremental value is expected in a timeboxed period?

  • APRINCE2
  • BWaterfall
  • CScrum (correct answer)
  • DSLDC
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Scrum

Topic 1 Β· Question 117

A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?

  • AEstablish a minimally viable product.
  • BPrepare new knowledge base documentation. (correct answer)
  • CUpdate the project baseline and schedule.
  • DPeriodically review vendor performance.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Prepare new knowledge base documentation.

Topic 1 Β· Question 118

Which of the following methods frequently delivers new code in an automatic way for development projects?

  • AAutomated testing
  • BCI/CD process (correct answer)
  • CValidation checks
  • DDeploy sprint
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: CI/CD process

Explanation

CI/CD automates integration, testing, and deployment to deliver changes consistently and rapidly.

Topic 1 Β· Question 119

When trying to calculate the expected monetary value for using a particular vendor, which of the following charts would be BEST to use?

  • ADecision tree (correct answer)
  • BFishbone
  • CHistogram
  • DPareto
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Decision tree

Topic 1 Β· Question 120

Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?

  • AStart-to-finish
  • BStart-to-start (correct answer)
  • CFinish-to-start
  • DFinish-to-finish
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Start-to-start

Topic 1 Β· Question 121

Which of the following is a consideration when determining a project's ESG factors?

  • AProject management methodology
  • BIT infrastructure security
  • CProper accounting practices
  • DCorporate values compliance (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Corporate values compliance

Explanation

Recovery point objective defines the maximum acceptable data loss measured in time.

Showing questions 101–120 of 187 Β· Page 6 of 10