Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?
- ANegotiate to get more of the team member's available time. (correct answer)
- BAssign the team member to work overtime to finish the task.
- CSpeed up completion of the task by assisting the team member.
- DHave the project manager complete the task.
Reveal answer & explanationHide answer
The correct answer is A. Option A: Negotiate to get more of the team member's available time.