Topic 1 Β· Question 42 Β· Select all that apply

A program manager is reviewing the project portfolio and prioritizing each project based on the company’s strategic plan. Which of the following should be considered in this evaluation? (Choose two.)

  • ACompany vision (correct answer)
  • BGlobal environment
  • CBrand value
  • DMission statement (correct answer)
  • EPortfolio budget
  • FLocal legislation
Reveal answer & explanation
Correct answer: A, D

The correct answer is A, D. Option A: Company vision Option D: Mission statement

Topic 1 Β· Question 43

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

  • AGantt chart (correct answer)
  • BMaintenance window schedule
  • CFunctional requirements
  • DTest results
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Gantt chart

Topic 1 Β· Question 44

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

  • ADecision board
  • BWhiteboard
  • CTask board (correct answer)
  • DDashboard
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Task board

Topic 1 Β· Question 45

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

  • AResource allocation
  • BCommunication security
  • CTechnological factors
  • DCultural differences (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Cultural differences

Topic 1 Β· Question 46

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following: Which of the following was the initial cause of the issue?

Exhibit 1 for question 46
  • AInadequate memory
  • BIncorrect configuration
  • CLack of infrastructure
  • DInadequate instructions (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Inadequate instructions

Topic 1 Β· Question 47

Which of the following describes three-tier architecture?

  • AConceptual, design, and implementation stages
  • BPresentation, application, and data processing (correct answer)
  • CNetwork, software, and security
  • DDevelopment, testing, and production environment
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Presentation, application, and data processing

Topic 1 Β· Question 48

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

  • AImplement the change.
  • BApprove the test plan.
  • CNotify customers.
  • DDevelop a rollback plan. (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Develop a rollback plan.

Topic 1 Β· Question 49

Which of the following offers administrators more direct control over operating systems?

  • AInfrastructure as a service (correct answer)
  • BSoftware as a service
  • CFunctions as a service
  • DPlatform as a service
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Infrastructure as a service

Topic 1 Β· Question 50 Β· Select all that apply

Which of the following items must be protected as PII? (Choose two.)

  • AJob title
  • BHome address (correct answer)
  • CWork phone number
  • DTime zone
  • EDate of birth (correct answer)
  • FBlood type
Reveal answer & explanation
Correct answer: B, E

The correct answer is B, E. Option B: Home address Option E: Date of birth

Topic 1 Β· Question 51

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

  • ACreation of a social news forum
  • BManagement directives to use the new system
  • CNew user kickoff meeting
  • DMonthly feedback and training sessions (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Monthly feedback and training sessions

Topic 1 Β· Question 52

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis: Based on the chart, which of the following is the current status of the project?

Exhibit 1 for question 52
  • ABehind schedule and over budget (correct answer)
  • BBehind schedule and under budget
  • CAhead of schedule and over budget
  • DAhead of schedule and under budget
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Behind schedule and over budget

Topic 1 Β· Question 53

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

  • AStrong projectized organization
  • BMedium risk
  • CLack of resources
  • DMultiple undefined tasks (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Multiple undefined tasks

Topic 1 Β· Question 54

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains: Purpose - Scope of work - Location of work - Period of performance - Deliverables schedule - Applicable standards - Acceptance criteria - Special requirements - Payment schedule - Which of the following documents did the client provide to the project manager?

  • ARFP
  • BWBS
  • CSLA
  • DSOW (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: SOW

Topic 1 Β· Question 55

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM’s time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

  • APerform a root cause analysis.
  • BOrganize a stakeholder meeting.
  • CEscalate the issue to the CCB.
  • DContact the PMO for assistance. (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: Contact the PMO for assistance.

Topic 1 Β· Question 56

A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

  • AA project manager assigned the wrong resources.
  • BA project manager did not release the resources. (correct answer)
  • CA project manager did not remove the system access.
  • DA project manager did not provide the project sign-off.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: A project manager did not release the resources.

Topic 1 Β· Question 57

Which of the following requires the MOST availability from the business team?

  • ASDLC
  • BScrum (correct answer)
  • CPRINCE2
  • DWaterfall
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Scrum

Topic 1 Β· Question 58

Which of the following software programs would be BEST to use to store information related to business transactions?

  • ARecord management system
  • BCustomer relationship management
  • CEnterprise resource planning (correct answer)
  • DContent management system
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Enterprise resource planning

Topic 1 Β· Question 59

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

  • AWork with the project scheduler to update the project timeline. (correct answer)
  • BCommunicate to the stakeholders about the updated timeline.
  • CAsk the development team to fast-track upcoming activities.
  • DAdd two resources so the critical activities will finish on time.
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Work with the project scheduler to update the project timeline.

Topic 1 Β· Question 60

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

  • AMemorandum of understanding
  • BRequest for information
  • CStatement of work (correct answer)
  • DNon-disclosure agreement
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Statement of work

Topic 1 Β· Question 61

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

  • ACreate a list of tasks and share it with the team. (correct answer)
  • BResend the scope of work to the team.
  • CReview the Gantt chart weekly with the team.
  • DHave the project sponsor meet with the team.
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Create a list of tasks and share it with the team.

Showing questions 41–60 of 187 Β· Page 3 of 10