A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
- AMake an impact assessment. (correct answer)
- BPrepare a new purchase order.
- CSelect a new vendor.
- DCreate a risk register.
Reveal answer & explanationHide answer
The correct answer is A. Option A: Make an impact assessment.