πŸ”

PK0-005 β€” questions

Page 4 of 10 Β· 187 total questions.

Topic 1 Β· Question 62

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

  • AMake an impact assessment. (correct answer)
  • BPrepare a new purchase order.
  • CSelect a new vendor.
  • DCreate a risk register.
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Make an impact assessment.

Topic 1 Β· Question 63

Which of the following BEST identifies the intent and purpose of a project closeout report?

  • ATo provide documentation of lessons learned
  • BTo document variances from the initial project baseline
  • CTo validate that a project has been successfully completed (correct answer)
  • DTo release resources and terminate all access rights
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: To validate that a project has been successfully completed

Topic 1 Β· Question 64

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

  • AROI. (correct answer)
  • BSOW.
  • CRFI.
  • DRFP.
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: ROI.

Topic 1 Β· Question 65 Β· Select all that apply

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Choose two.)

  • ARisk report
  • BDefect log
  • CIssue log
  • DBacklog (correct answer)
  • EChange log (correct answer)
  • FProgress report
Reveal answer & explanation
Correct answer: D, E

The correct answer is D, E. Option D: Backlog Option E: Change log

Topic 1 Β· Question 66

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

  • ASOW (correct answer)
  • BRFI
  • CRFQ
  • DWBS
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: SOW

Topic 1 Β· Question 67

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

  • ADetermine budget constraints.
  • BValidate the business case.
  • CUpdate the project charter. (correct answer)
  • DCreate a project schedule.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Update the project charter.

Topic 1 Β· Question 68

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

  • AScope creep (correct answer)
  • BCollecting requirements
  • CDecision-making
  • DProject change
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Scope creep

Topic 1 Β· Question 69

Which of the following BEST illustrates how team members with different roles should interact on the team?

  • ASOW
  • BWBS
  • CRACI (correct answer)
  • DPERT
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: RACI

Topic 1 Β· Question 70

For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

  • AResource plan
  • BOrganizational chart
  • CProject charter
  • DRACI chart (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: RACI chart

Topic 1 Β· Question 71

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

  • AKanban board
  • BPareto chart
  • CIshikawa diagram (correct answer)
  • DDecision tree
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Ishikawa diagram

Topic 1 Β· Question 72

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

  • ADashboard (correct answer)
  • BGantt chart
  • CWork breakdown structure
  • DRequirements Traceability Matrix
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Dashboard

Topic 1 Β· Question 73

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

  • ACritical paths
  • BResources
  • CMilestones (correct answer)
  • DWork breakdown structures
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Milestones

Topic 1 Β· Question 74

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

  • ADecline because it is not included in the project scope.
  • BAssess the impact of the request and create a change request. (correct answer)
  • CCreate new functional and non-functional requirements for mobile devices.
  • DRevise the baseline of the project plan by adding the new requirements.
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Assess the impact of the request and create a change request.

Topic 1 Β· Question 75

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

  • AA risk budget
  • BA risk impact
  • CA change request
  • DA contingency plan (correct answer)
Reveal answer & explanation
Correct answer: D

The correct answer is D. Option D: A contingency plan

Topic 1 Β· Question 76

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

  • AProcurement
  • BCommunication
  • CQuality assurance (correct answer)
  • DRisk
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Quality assurance

Topic 1 Β· Question 77

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

  • AEscalate the communication issues.
  • BImplement a communication platform.
  • CReview the communication plan. (correct answer)
  • DTalk with the head of the PMO.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: Review the communication plan.

Topic 1 Β· Question 78

An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

  • AThe ticket system provided access by default without any approval.
  • BThe project manager did not perform proper project planning.
  • CThe system is lacking proper access controls. (correct answer)
  • DSensitive data was incorrectly classified during the audit process.
Reveal answer & explanation
Correct answer: C

The correct answer is C. Option C: The system is lacking proper access controls. This option keeps traffic private / properly secured as required.

Topic 1 Β· Question 79

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens’ complaints. Which of the following solutions would be BEST?

  • AEnterprise resource planning and end user applications
  • BElectronic document and record management systems (correct answer)
  • CCustomer relationship management and databases
  • DContent management and financial systems
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Electronic document and record management systems

Topic 1 Β· Question 80

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

  • AValidate against the scope statement and ask for sign-off. (correct answer)
  • BRun a control chart to ensure the quality of the deliverables.
  • CReview the risk register and close up residual risks.
  • DStart the training and handoff for the operations team.
Reveal answer & explanation
Correct answer: A

The correct answer is A. Option A: Validate against the scope statement and ask for sign-off.

Topic 1 Β· Question 81

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

  • ASmoke testing
  • BRegression testing (correct answer)
  • CUnit testing
  • DUser acceptance testing
Reveal answer & explanation
Correct answer: B

The correct answer is B. Option B: Regression testing

Showing questions 61–80 of 187 Β· Page 4 of 10